A knockdown rebuild means demolishing your existing house and building a new one on the same block. You keep the street, the school zone and the neighbours, and you get a home designed for the way your family lives now. In NSW it works best when one licensed builder carries the project from the demolition approval through to handover, because the demolition and the new build are two separate approvals, and the gaps between them are where budgets and timelines slip. At McArthur Constructions Group, a licensed Sydney builder, demolition, structural work, plumbing, electrical, waterproofing, tiling, cabinetry and project management all sit within our scope, and we back the finished work with a 7-year workmanship warranty.
TL;DR
- A knockdown rebuild is two approvals and two phases: demolition, then new construction. In NSW you cannot demolish until approval for the new home is granted.
- Check the block first: heritage, trees, flooding, bushfire, easements, drainage and asbestos decide what is possible and what it costs.
- Budget for the whole project, not just the build: demolition, asbestos, service disconnections, certifier and authority fees, temporary housing, fencing, driveway, landscaping and a contingency.
- Fund it with a construction loan that releases money in stages, and get your lender’s written approval before any demolition starts.
- One builder responsible for demolition, structure and finishes keeps the handovers between stages under control.
Table of Contents
- What a knockdown rebuild actually is
- Knockdown rebuild or renovation or extension?
- Check the block before you draw anything
- The five phases in NSW
- What a knockdown rebuild costs
- Paying for it: construction finance
- How long you will be out of the house
- Mistakes that cost owners money
- Our view on knockdown rebuilds
- Talk to a builder who handles the whole project
- FAQ
- Sources
What a knockdown rebuild actually is
The Australian Bureau of Statistics defines a knock-down rebuild as an approval to demolish an existing dwelling that is linked to an approval to build new dwellings on the same property within three years. Taking down only part of a house is classed as an alteration and addition, not a knockdown rebuild.
The same ABS release shows how common the approach is. Between July 2019 and June 2025, 58.3% of projects were one-for-one replacements, and the rest added dwellings, for an average of 2.1 dwellings approved per dwelling demolished. The average approval value for a detached knockdown rebuild house was $729,121, against $355,478 for other detached houses. That gap is worth reading carefully: these are new, full-size homes on established land, often in the more expensive suburbs.
People usually go this way for one of three reasons: the structure has problems that make repair uneconomic, the layout would need so much structural change that renovating costs nearly as much as starting again, or the block can take more than one dwelling. The ABS notes these same drivers, including a more cost-effective alternative to a larger renovation involving structural layout changes.
Knockdown rebuild or renovation or extension?
The honest test is how much of the existing house you would keep. If the footprint, roof and structure are sound and you want more space, an extension or a full home renovation keeps what is good and adds what is missing. If you would be moving most walls, replacing the services, fixing the slab and rebuilding the roof, you are paying for a new house inside an old shell, and starting clean often makes more sense.
| Situation | Usually points to |
|---|---|
| Sound structure, need one or two more rooms | Extension or home addition |
| Good bones, tired kitchen, bathrooms and finishes | Renovation |
| Structural or layout changes throughout, plus failing services | Knockdown rebuild |
| Large block that could take more than one dwelling | Knockdown rebuild, or a new build alongside the existing house |
| Heritage-listed home or conservation area | Renovation or restoration, as demolition is heavily restricted |
A builder who does both renovation and new construction can price the two routes against each other for your block, which is the comparison you actually need before committing.
Check the block before you draw anything
The NSW Government’s MyHome Planner tells owners to check heritage listings, tree preservation orders, underground utilities, excavation needs and drainage or stormwater issues before going further. It also points to the Section 10.7 planning certificate, which sets out zoning, planning controls, land contamination, flooding and bushfire-prone land for your lot. Order it early: it can change what you are allowed to build, and how.
Practical points that catch Sydney owners out:
- Heritage and conservation areas. In a heritage conservation area, the NSW Demolition Code allows only limited demolition without full council assessment, such as dwelling walls not facing a primary road, outbuildings and internal walls. Whole-house demolition in these areas needs a council development application, with no guarantee of approval.
- Slopes and rock. Many Mosman, Vaucluse and Northern Beaches blocks fall steeply or sit on sandstone. Excavation and retaining walls can cost more than the demolition itself.
- Easements and drainage. Pipes and easements across the site affect where machines can work and where the new footprint can go.
- Asbestos. Homes built before 1990 may contain it, and it must be identified before demolition is planned.
If you own the property jointly with a partner, or are buying into one, it also pays to settle who owns what before you commit hundreds of thousands of dollars to the block. Couples in this position sometimes put the arrangement in writing through a binding financial agreement in NSW, so the rebuild sits on clear ground.
The five phases in NSW
MyHome Planner lays the journey out in five phases: Plan, Approve, Demolish, Build and Post-build. Here is what each involves in plain terms.

1. Plan
This is finances, site inspections and choosing your builder and demolition contractor. Get the feasibility right here and the rest runs far more smoothly. Settle your total budget, confirm what the site allows, and decide whether you want a single builder carrying the whole job. With us, demolition, carpentry, structural alterations and the service trades are covered under one contract and one project manager, so you are not coordinating separate trades yourself.
2. Approve
You need two approvals: one for demolition and one for the new home. MyHome Planner is clear that you cannot demolish until approval for your new home has been granted. Design and documentation is the longest part of this phase and depends on how complex the house and block are. Allow months, not weeks.
A new home can be approved either by council as a development application, or, where the site and design meet the criteria, as complying development by a private certifier. Your design must fit the planning controls for your zone, which is why the site checks come first.
3. Demolish
A house, garage and swimming pool can usually be demolished under a complying development certificate, provided the site is not excluded by heritage, flooding or other constraints. The NSW demolition rules set conditions you should expect your demolisher to meet:
- all essential services disconnected to the relevant authority’s requirements;
- a dilapidation report on an adjoining wall where you are demolishing a wall within 900 mm of the boundary and the neighbour’s wall is also within 900 mm;
- a waste management plan given to the certifier at least two days before work starts;
- erosion and run-off controls in place before work begins;
- work only between 7 am and 5 pm Monday to Saturday;
- work to Australian Standard AS 2601-2001, The Demolition of Structures;
- neighbours notified before demolition begins.
All of this comes from the NSW demolition rules for exempt and complying development. The owner is also responsible for getting a clearance certificate from the demolisher confirming the land is safe and free of hazardous material, and council may require a security deposit or bond against damage to council property.
Asbestos work is regulated by SafeWork NSW. The regulator states that from 1 March 2025 a person can be prosecuted for allowing a worker to carry out licensed demolition work without the approved training, and that new units of competency for demolition licence holders took effect on 1 July 2025. In practice, this means your demolition contractor must hold the right licence and have trained workers. Ask to see it.
Realestate.com.au puts demolition at two to four weeks, depending on asbestos, weather, site access and salvage.
4. Build
Once the slab is ready, you need a construction certificate and a principal certifier, and your lender must approve the next stage. Building then proceeds through the familiar stages: slab, frame, lock-up, fixing and completion. This is where finish quality matters most. Waterproofing, tiling and cabinetry done well are what you live with for decades, and on our own builds we stand behind that work with a 7-year workmanship warranty.
5. Post-build
The certifier issues the occupation certificate, you do a handover inspection, and landscaping, driveway and fencing are completed if they were outside the main contract. Walk through with a written defect list before you move in.
What a knockdown rebuild costs
Published guides give very wide ranges because every block is different, so treat any single number with caution. The most reliable official anchor is the ABS figure above: an average approval value of $729,121 for detached knockdown rebuild houses nationally from July 2019 to June 2025. That is the value of the new building, and it excludes demolition, site works, finance costs and living costs during the project.
In Sydney, the new house is usually priced per square metre, and the cost rises with finish level, steep sites, basements and structural complexity. The costs sitting outside the build price are the ones owners forget:
- demolition, with a higher cost for pools, granny flats or large areas of concrete;
- asbestos testing and removal where the house predates 1990;
- disconnecting and reconnecting water, sewer, gas, electricity and telecommunications;
- surveys, engineering, certifier and council fees;
- fencing, driveway, landscaping and appliances if they sit outside the contract;
- temporary accommodation and holding costs;
- a contingency.
A finance guide for Australian construction lending suggests a contingency of 5 to 15% and lists these same budget layers. On a rebuild with an older house and a sloping site, plan towards the upper end.
Can you do it for $300,000 or $350,000?
On an established Sydney block, not realistically for a full-size new home plus demolition and site costs. The ABS average for a new detached knockdown rebuild house is more than double that figure. A smaller dwelling such as a granny flat is a different project with different rules, and a renovation or extension can sit at lower budgets than a whole new house.
The cheapest way to demolish
The cost is driven by what is in the house and how reachable the site is: asbestos, access for machines, the amount of material and extra structures. Salvaging items such as bricks, timber and fittings can save money and reduce environmental impact. The NSW EPA describes deconstruction as taking a building apart so the maximum amount of material can be sold, reused or recycled, and sets out a planning process starting with a site survey and a materials management plan. Separating clean concrete, timber and metal at the site also keeps mixed-waste disposal costs down. The cheapest sensible demolition is a licensed, well-planned one. An unlicensed shortcut with asbestos is never cheap.

Paying for it: construction finance
Most owners fund a knockdown rebuild with a construction loan. One Australian finance guide describes it as a construction loan with demolition and land-only security controls: the lender’s security moves from your established home to a vacant site, then to an incomplete building, then to the finished house. The same guide advises getting your existing lender’s written demolition approval and formal construction approval before committing to demolition.
Funds are released in stages as the build progresses, with interest charged only on the amount drawn, and lenders commonly lend up to 80% of the completed value. Lenders and rates change, and your borrowing capacity depends on your own finances, so speak to your lender or a licensed mortgage broker for a quote on your situation.
Two practical points. First, a fixed-price contract with clear stage payments makes it far easier for a lender to assess the project. Second, an investor rebuilding to rent or sell should read the rental property renovation guide to weigh what each spend returns.
How long you will be out of the house
Plan for a long project. Demolition is the short part. Design, approval and construction make up the bulk. Realestate.com.au reports a typical build of around six months for simpler projects, with owners out of the house for at least four months and sometimes more than 12. A larger, custom Sydney home will sit toward the long end, so line up rental accommodation with a margin and keep it in the budget.
The ABS also found an average lag of 5.7 months between the demolition approval and the building approval, which shows how often owners sequence these steps differently. Whatever sequence you choose in NSW, the new-home approval must come first.
Mistakes that cost owners money
- Pricing only the build. The new house is the largest line, not the only one. Ask every builder what is excluded.
- Skipping the 10.7 certificate. A flood or bushfire notation found after design can force a redesign.
- Demolishing too early. Without the new-home approval and lender sign-off you risk holding a vacant block and a loan you cannot draw on.
- Underestimating asbestos. Test early so it does not become a surprise in week one.
- No neighbour plan. Dilapidation reports and notification protect you if a boundary wall is damaged.
- Too many contractors. Each handover between demolisher, builder and trades is a place for delays and blame. A single accountable builder narrows that.
Our view on knockdown rebuilds
Most of the owners who come to us have a good location and a house that no longer fits. The decision is rarely about the house. It is about whether the money is better spent starting fresh or reshaping what is there.
We start with the block and the numbers, and we treat demolition as the opening stage of the build, not a separate job. We carry out demolition, carpentry, structural alterations, plumbing, electrical, waterproofing, tiling and cabinetry ourselves, managed as one project, so the handover between stages does not become your problem.
What we care about is the finish: premium materials, careful detailing and workmanship we will stand behind for seven years. A new home should feel considered from the first day, and look right on its street in Mosman, Vaucluse, Pymble or Wahroonga.
McArthur
Talk to a builder who handles the whole project
If you are weighing a knockdown rebuild on the Eastern Suburbs, Lower or Upper North Shore, Northern Beaches or Hills District, start with our new builds page. If you are still deciding between rebuilding and reshaping what you have, our renovation advice page is the place to begin. We are a licensed Sydney builder, our scope covers demolition through to cabinetry and finishes under complete project management, and our work carries a 7-year workmanship warranty.

Bring your block address and what you want from the new home, and we will talk through how the project would run.
FAQ
Do I need approval to demolish my house in NSW?
Yes. Demolition needs either a council development approval or a complying development certificate from a private certifier, depending on the site. Heritage items, conservation areas, flood-prone land and some bushfire-prone land generally rule out the complying route. In NSW you also cannot demolish until the approval for your new home has been granted.
How long does a knockdown rebuild take?
Demolition itself usually takes two to four weeks. The longest parts are design and approvals, then construction. Owners are commonly out of the house for at least four months and sometimes more than a year, so plan accommodation with a buffer.
Is it cheaper to knock down and rebuild than to renovate?
It depends on how much of the house you would keep. When the structure is sound, renovating or extending usually costs less. When you would be changing the layout, structure and services throughout, a rebuild can be the more cost-effective route, as the ABS notes for larger renovations involving structural layout changes.
Can I live in the house while it is rebuilt?
No. The old house is demolished, so you need somewhere else to live until the new home has its occupation certificate. Include rent and storage in your budget from the start.
Sources
- Approvals of Knock-Down Rebuilds, Australian Bureau of Statistics
- Knockdown and rebuild considerations, MyHome Planner, NSW Planning Portal
- Knockdown Rebuild phases, MyHome Planner, NSW Planning Portal
- Demolition of buildings: rules for exempt and complying development, NSW Planning
- Demolition, SafeWork NSW
- Plan and conduct a house deconstruction, NSW EPA
- 2024 guide to knock down rebuilds, realestate.com.au
- Construction and Renovation Finance Guide Australia, RateChallenge
- Knockdown Rebuild Cost Sydney 2026, RyRo Loan Centre
One Response